The minutes of the September meeting and the payroll and invoices were approved.
Expenses included $500 to DEP for the annual National Pollution Discharge Elimination System (NPDES) permit fee.
Mr. Lingenfelter and Mr. Wolf presented the engineer's report.
Completed work at the Wastewater treatment Plant site includes: Erosion and sedimentation controls, sediment basin and embankment excavation, clearing and grubbing, SBR/Control Building area layout survey, SBR, Control Building and Mechanical Building slab excavations, and half of the access road excavation.
Completion of the access road excavation will be finished shortly. Pile testing and placement of piles and footings will be undertaken next, followed by construction of a 6" water line and placement of a 12" intermediate effluent line to connect the future Ultraviolet system and the utility water storage tank.