Work is slated to begin September 1, with mobilization for the project through September 8.
Site clearing for the new construction is planned to begin September 9 and run through September 15.
From September 23 to 29, the contractor will work on removing topsoil and erosion and sediment control.
Excavation for the structural piles required for construction is scheduled from September 30 to October 13 and work on the piles from October 14 to November 10.
After that the contractor intends to work on the slab for the SBR (Sequencing Batch Reactor) process. The slab is expected to be poured December 2.